Nalanda English Medium Higher Secondary School

Bhilai, Durg (C.G.) 490024

A large arched steel roof over the central courtyard, with walkway bridges linking the blocks. We took the job from foundation and steel fabrication through erection to the last roofing sheet.

Roof
Arched steel trusses, 58 ft 10 in span, 3 m rise
Extras
Two walkway bridges, turbine ventilators
Our work
Fabrication, erection and roofing
Nalanda English Medium Higher Secondary School

Work by stage

01

Design

The design drawing fixed the main sizes: a span of 58 ft 10 in, a roof rise of 3 m and an arch length of about 62 ft. Both pictures are design renders, not site photos.

Design render: 58 ft 10 in span, 3 m roof rise
Design render: covered children’s wash-area shed (proposed)
02

Foundation and anchor bolts

Each footing was cast with a reinforcement cage for the column and anchor bolts set on a base plate, checked for level and position before concreting.

Foundation with anchor bolts and column reinforcement
03

Fabrication in our yard

Roof trusses and walkway bridge frames were cut, welded and assembled on the ground, then given red-oxide primer.

Steel trusses fabricated and primed in the yard
Walkway bridge frame fabricated in the yard
04

Erection with a crane

Arch trusses were lifted one by one with a hydraulic crane, bolted and welded to the columns and braced to their neighbours.

Crane lifting the roof arches into position
Arches and walkway bridges rising over the courtyard
Roof arches taking shape, seen from the terrace
05

Steel frame complete

With all arches, purlins and both walkway bridges in place, the frame was painted blue and ready for sheeting.

Steel roof frame complete
06

Work at height

The crew worked from the crane’s man-basket to fix, fasten and finish the roof at height.

Crane lifting material at height
Crew working from the crane basket
07

Roof sheeting and ventilation

Red profiled sheets laid along the curve of the arches, turbine ventilators along the ridge and light panels for daylight.

Roof sheeting under way
Finished sheeting and ventilators
08

Finished roof

The courtyard, where the school buses park, is now covered from sun and rain.

Finished roof, from inside the courtyard